The Chariton City Council approved the low Bid from Irvinbilt Company for the new Municipal Aquatic Center.

Irvinbilt Company from Chillicothe, MO. built the new pool with a base bid of $2,849,000.  The Chariton City Council, Chariton Park and Recreation Board, the Swimming Pool Committee, and the Chariton Recreation Department have put together and endorsed the following list of items that they would like to see added to the new aquatic facility and Bingham Park if funds were available. Early planning discussions included some of these items in the pool design, but they were eliminated in order to trim overall project costs. See Details.  The layout was approved by the Swimming Pool Committee.  The Funding for the new project is from a 1 cent special option sales tax passed in every city in Lucas County.  If you have any questions contact Committee Members or Recreation Director.


Add. Alt. #2 - Sand Play Area                                                                                  $     40,000                                                Add. Alt. #3 - Wash Down Shower                                                                         $       3,000                                            Add. Alt. #4 - Seeding                                                                                                $    10,000                                                Add Alt. #8 - Basketball Goal                                                                                    $      1,800                                                Add. Alt #10 - Sunshade @ Concessions                                                               $      3,000                                       Total Bid Plus Additions                                                                                          $2,906,800

The Council did not approve several additional items that would be very nice to have at the new pool.  Please review the wish list below. 

ITEMS NOT APPROVED                                                                                                                                                       Add. Alt. #1 - Sand Volleyball                                                                                    $   30,000                                                Add. Alt. #5 - Sodding                                                                                                 $   24,000                                       Add. Alt. #6 - Tube Slide                                                                                             $   60,000                                         Add Alt. #7 - Seamless   Flooring                                                                               $   23,000                                         Add. Alt #9 - Floatables                                                                                               $   22,900

Irvinbilt Company has completed the project and the pool was dedicated on July 4, 2000.                                                                                              

               
    TOTAL PROJECT COST          $2,906,800

Click on Thumbnail to see larger picture.

Charweb3.jpg (95791 bytes)

Home          What New      City Staff            Labor Survey        Industrial Park

Last updated  11/08/05